Woodside's multibillion-dollar Scarborough gas megaproject was 78% complete at the end of the fourth quarter, with the final Pluto Train 2 modules arriving at the Pluto LNG site in December.
Archer said it’s expected that LNG Canada’s first “train” (processing unit ... and LNG processing equipment and modules are expected to arrive on site in 2025. Work is also underway ...
The final Pluto Train 2 modules arrived at the Pluto LNG site in December. Scarborough remains on target for its first LNG cargo in 2026. The earlier stage Trion project was 20% complete at the ...
2024--The Scarborough Energy Project has passed another significant milestone with the final Pluto Train 2 modules arriving at the Pluto LNG facility in Karratha, Western Australia. The asset swap ...
including the arrival of the final Pluto Train 2 modules for our Scarborough Energy Project, which remains on track for first LNG in 2026. We were also pleased to welcome JERA, another strategic ...
Baker Hughes to supply liquefaction solutions utilizing NMBL™ module ... train systems, and signs multi-year services frame agreement to support phases 1 and 2 of Plaquemines LNG projectAs ...
The Maharashtra go to also signed an agreement with FUEL (Friends Union for Energising Lives) to train 5,000 youth in ... of liquefied natural gas (LNG) from the United States and Nigeria as ...
Japan's biggest oil and gas explorer, Inpex Corp , said on Thursday it aims to make a final investment decision (FID) on its ...